Route 2020 Subway Drilling Begins in Dubai on October 2017

Route 2020 Subway Drilling Begins
- Drilling work on the Route 2020 was launched on Tuesday, 24th October, by Sheikh Mohammed bin Rashid Al Maktoum
- A giant tunnel digger, the Wegisha Expo 2020, has been deployed to bore through underground stretches and connect it with a 11.8km elevated track
- The tunnel will be between 12.5m and 36m underground and excavation is expected to be completed by December 2018
- Work on the new link will connect the Dubai Metro Red Line service on Sheikh Zayed Road to the expo grounds in Dubai South
- Sheikh Mohammed bin Rashid Al Maktoum is the Vice President and Prime Minister of the UAE and Ruler of Dubai
- Route 2020 is the 15-km extension of Dubai Metro’s Red Line to the Dubai Expo 2020 venue
- Route 2020 is expected to handle 20% of people coming to the expo, with trains ferrying 35,000 commuters daily during the week and 47,000 on weekends
- Along Route 2020 will be five stations above ground, two underground stations, an interchange area, and an expo station
- Infrastructure, civil and electromechanical construction of Route 2020 with all railway works is expected to be completed in July 2019
Al Shaheen School in Al Foah, Abu Dhabi
DHL Express Courier in Abu Dhabi Office Address and Timings
Online appointment system at Pakistan Consulate in Dubai
Hamooda Bin Ali School in Abu Dhabi Island, Abu Dhabi